SOUTHEAST ASIA CONSTRUCTION10 Sep 2019
LTA awards civil contracts for Singapore’s Jurong Region Line project
Views: 1553

Singapore’s Land Transport Authority (LTA) has awarded two civil contracts for the construction works of five Jurong Region Line (JRL) stations and their associated viaducts. 

One of the contracts, totalling S$465.2 million, is for Shanghai Tunnel Engineering Co (Singapore) Pte Ltd. It comprises works to design and construct Choa Chu Kang, Choa Chu Kang West and Tengah stations with a 4.3-km viaduct between Choa Chu Kang and Tengah along Choa Chu Kang Ave 3. This includes addition and alteration works to the existing Choa Chu Kang station on the North-South Line, to integrate it with the new JRL station.

LTA said that Shanghai Tunnel Engineering has an established track record of railway infrastructure projects for the Circle Line, Downtown Line and Tuas West Extension. The company is also involved in the ongoing construction of the Thomson-East Coast Line (TEL) Shenton Way, Katong Park and Bayshore stations and tunnels, as well as a stretch of tunnel from Woodlands Avenue 12 to the TEL Mandai Depot.

The other contract, totalling S$274.3 million, is for Eng Lee Engineering Pte Ltd - Wai Fong Construction Pte Ltd Joint Venture (JV). It comprises works to design and construct Hong Kah and Corporation stations with a 3.4-km viaduct between them.

The JV is currently working on the ongoing construction of the TEL Mount Pleasant station and tunnels. Wai Fong Construction is also involved in the ongoing construction of the North-South Corridor between Victoria Street and Kampong Java Road, as well as the TEL Tanjong Rhu station and tunnels.

Construction works for the two new contracts are expected to start in 2020 and slated for completion in 2026.

The JRL is Singapore’s seventh MRT line, and is scheduled to open in three stages starting from 2026. According to LTA, it will be an elevated line serving both existing and future developments in the western part of Singapore.

The JRL will be approximately 24 km long and have 24 stations, including three interchange stations at Boon Lay, Choa Chu Kang and Jurong East MRT stations. This provides direct connectivity between the northwestern and western regions of Singapore.

In the initial years, the JRL is expected to serve 200,000 daily commuters. This is forecast to increase to more than 500,000 daily commuters in the longer term, once future developments in the area are realised.